Work tasks on this project generally include the replacement of 10 existing wood pole 115 kV H-frame transmission structures with new steel pole 115 kV H-frame transmission structures to increase line reliability. Procurement of all materials, including steel poles, is included in the contractor’s scope. Structure locations are difficult to access due to terrain, so access (whether temporary or permanent) is expected to be a considerable portion of the work. All proposals shall include a detailed breakdown of access costs and assumptions to allow the City of Shasta Lake to more effectively compare bids. All other items or details not mentioned above that are required by the Plans or the Contract Documents shall be procured furnished, fabricated, constructed, or installed. The Engineer’s Estimate for this work is $650,000.00.
|
|
12/20/2021 8:00 AM
|
|
1/27/2022 2:00 PM
|
|
Trent Drenon, P.E., Assistant Electric Utility Director 530-275-7400
|
|
Yes
|
|
None
|
|
The City of Shasta Lake provides Contract Documents for projects electronically and free of charge via the internet at www.ciplist.com. This site is the only approved location for prospective bidders to obtain official City Contract Documents. NO HARD COPY CONTRACT DOCUMENTS WILL BE AVAILABLE FOR PURCHASE.
|
|
7am to 4pm M-F
|
|
Contractors and Subcontractors shall possess appropriate Contractor’s Licenses for their trade at the time the contract is awarded.
|
|
A prebid conference is scheduled between staff and interested bidders at the City of Shasta Lake Corporation Yard, 4332 Vallecito Street (2nd Floor), Shasta Lake, on Tuesday, January 11, 2022 at 10:00 a.m., at which time the project will be reviewed. All interested bidders are encouraged to attend.
|
|
|
|